"I don't think you should have a set game plan, it's going to have to be very fluid, of what comes up and meeting the needs of the people." Councilmember Neil Layton said that in March, when the San Carlos City Council was discussing how to support downtown businesses during the Harrington Park construction.
Six months later, you can see what "fluid" turned into. The park on the 700 block of Laurel Street is fenced, and the City expects to finish it in early 2027. Since spring, the City has moved the park's jobs to other spots. Big gatherings went to Wheeler Plaza, seating went onto the Laurel sidewalk, and Laurel Street itself carries the fall events. Taken together, these stopgaps look a lot like the downtown the finished park is supposed to support, only arriving first and in pieces.
What sits behind the fence, and for how long
The redesigned Harrington Park will have a multi-purpose plaza for community gatherings, a new building with public restrooms and storage, public seating, and a rain garden with a grove of trees. The City's updated FAQ also lists memorial bricks. Much of the work so far is out of sight. In late June, crews installed Silva Cells under the park. These underground structures give tree roots room to grow, and they also catch and filter stormwater.
The rules for living next to the site are short:
- Work hours: 8 a.m. to 5 p.m., Monday through Friday. The City will give advance notice of occasional off-hours work for utility connections, such as PG&E work.
- Parking: Four public spaces behind the park are being removed to make room for a new drop-off and loading zone.
- Truck access: Construction vehicles mainly use the alley behind Laurel Street and come in and out from Cherry and Olive Streets.
- Storefronts: Access to the Laurel Street shops stays open.
The park is only the first phase. The FAQ names the 700 block of Laurel Street as the next construction phase, and it says that timing has not been set. The planned Centennial Plaza on that same block is also on hold. The downtown plan website says its construction schedule is undetermined and depends on funding and Council direction. So "early 2027" is a finish date for the park, not for the whole downtown.
Wheeler Plaza took over the park's job
The first big change came before the groundbreaking. On May 3, the San Carlos Farmers' Market switched to a new layout. Since 2021, the market had run as a curbside "promenade." After feedback from downtown businesses, the City, the Urban Village Farmers' Market Association, and fire officials moved the booths away from the curbs. Some vendors moved into the Wheeler Plaza parking lot, which let Cherry Street reopen to traffic and parking. The City also added seating, umbrellas, and games. The market still runs Sundays from 9 a.m. to 1 p.m. on Laurel between Cherry Street and San Carlos Avenue.
In June, Wheeler Plaza became the crowd venue. About 500 fans came to the City's watch party for the USA's World Cup opener against Paraguay, and the City encouraged them to bring takeout from downtown restaurants. A second watch party, for USA vs. Bosnia & Herzegovina, used the same setup. A plaza gathering of that size is exactly what the finished park is meant to host. This summer it took place in a parking plaza while the park was behind a fence.
The Life on Laurel pop-ups kept the idea going on smaller nights. In mid-August, people played cornhole, checkers, Connect 4, and Jenga on the 700 block of Laurel on a Friday evening. The City says more pop-ups are planned through fall and winter. The only one currently listed is an obstacle-course fitness event on Thursday, October 1, from 5 to 7 p.m.
The sidewalk became the seating
The finished park promises public seating for relaxing or eating outdoors. Laurel Street got some of that first. Right after Hometown Days in May, the City set Adirondack chairs along Laurel, and it added more on August 18.
Other familiar things on the street have shifted too. Balancing Act, the blue figure statue, moved in early May to a new spot near Laurel and Cherry Streets. During the week of September 28, the City is installing two Downtown Revitalization information boards on the 700 block. One goes in the raised planter area near Diddams and the other near U.S. Bank.
The May parade showed events and construction can share the street
The best evidence that the fall calendar can run on a construction block came in May. Storm drain work had opened a trench across Laurel Street between Harrington Park and the Bank of America parking lot. For the May 16–17 Hometown Days weekend, the construction team covered the trench with steel plates so the parade could go through downtown. The sidewalk reopened by May 22, with a few small items still to finish.
Nothing on the fall calendar has been canceled. Here are the dates in order:
- Thursday, October 1, 5 to 7 p.m. The Life on Laurel obstacle-course fitness pop-up.
- October 10 and 11, 10 a.m. to 6 p.m. The San Carlos Art & Wine Faire, with more than 200 artists and crafters, live bands, wine, craft beer, and a Family Fun Zone. The organizer lists the footprint as Laurel Street between Arroyo and San Carlos Avenue, plus San Carlos Avenue between Elm and Laurel. Free parking and a shuttle run from PAMF at 301 Industrial Road, with drop-off at Laurel and San Carlos Avenue. The street closure map is linked from the City's faire FAQ page. Check it before you plan a route past the park block.
- October 23. Entry deadline for the City's Spooky Streets decorating contest.
- October 30, 4 to 5:30 p.m. The Goblin Walk on Laurel Street from San Carlos Avenue to Arroyo Avenue, for children 7 and under with an adult. Spooky Streets winners are announced the same day.
- November 14. Diwali appears on the City's events calendar, but the event page has no time, venue, or program yet.
- Friday, December 4, 5 to 8:30 p.m. Night of Holiday Lights on Laurel Street from San Carlos Avenue to Cherry Street, with the main stage on Cherry.
Every event on the list uses Laurel Street or a nearby cross street, not the park. Holiday Lights puts its main stage on Cherry, the street the farmers' market reopened in May.
The storefronts beside the fence
In March, the San Mateo Daily Journal reported that city staff expected two businesses to feel the park work most: Mama Coco and Faith & Spirits. Staff said they had been in touch with both, along with other nearby businesses. Mama Coco Restaurant is at 753 Laurel Street and Faith & Spirits is at 765 Laurel Street. In June, the Lunch Bunch program run with the Friends of the San Carlos Adult Community Center held its monthly outing at Mama Coco, right next to the construction. Diddams Party & Toy Store, at 700 Laurel Street, is the landmark the City used to describe where one of the new information boards goes.
The City formed its Downtown Prosperity Team in November 2025 to support businesses during and after both phases of construction. In March, staff described the measures under consideration:
- Promoting free parking at the Wheeler Plaza garage
- Working with underused parking lots so residents can park there during construction
- Possible long-term garage permits for employees of affected businesses
- Possibly leasing parking in the building SamTrans is leaving on San Carlos Avenue
- Lighting or art displays at construction zones
- Signs for businesses that start using their rear entrances
Staff presented these as options, not commitments. The City's project page calls the team's list a set of potential projects and says the team will put first the ones most likely to help. The Wheeler Plaza garage is the parking tip staff named first. It's also next to where the market, the watch parties, and the games ended up.
New businesses are still opening a block over. A September 25 local newsletter announced a grand opening for Casa Mia, a breakfast and casual dining spot at 677 Laurel Street, Suite B, on Saturday, September 26.
The City posts updates on its Downtown Revitalization blog. The latest construction status, dated September 30, reads "No Updates." Questions about the park work go to [email protected] or 650-802-4310.
If you own a home near Laurel Street and wonder how a multiyear downtown project could affect your plans, Jide Homes follows the San Carlos revitalization closely and can walk you through it. Request a Market Consultation, and we'll go over what the Harrington Park timeline and the still-unscheduled 700-block phase could mean for your street.